Tuesday April 22, 2025
Subpanel Support, LRU Mounting Planning (Electrical)
3.0 Hours

Previous - Index - Next

This afternoon I installed angle around the radio stack cut-out in the sub-panel and then connected the GTN mounting box with some screws. Unfortunately, I did realize that the angle on the bottom is going to interfere with the connector backshells on the audio panel, so I'll have to trim that back.

Then I assembled the remaining LRUs that will live in the panel area with their backshells.

Then I started planning where to mount various things.